DMD-2026-001

Smart public-facilities reporting platform

EvaluationIdea
Priority score
74

Score confirmed by the evaluation panel

Estimated cost
SAR 9.5M
Net present value
SAR 7.2M
Internal rate of return
⁦28.6%⁩
Payback period
⁦3.0⁩ years
Rank in the 2027 plan
#3

of ⁦9⁩ candidates

  1. Gate into «Submitted»DecisionGoDate11 February 2026DraftComplete
  2. Gate into «Initial review»DecisionGoDate1 May 2026SubmittedComplete
  3. Gate into «Feasibility»DecisionGoDate18 July 2026Initial reviewComplete
  4. Gate into «Evaluation»DecisionGoDate5 October 2026FeasibilityComplete
  5. Gate into «Committee review»DecisionNot held yetEvaluationCurrent phaseCurrent phase
  6. Gate into «Approved»DecisionNot held yet6Committee reviewNot started
  7. Gate into «Prioritized»DecisionNot held yet7ApprovedNot started
  8. Gate into «Converted to project»DecisionNot held yet8PrioritizedNot started
  9. 9Converted to projectNot started

The request as filed

What the requester wrote on the intake form

Problem
Reports of public-facility faults (lighting, water leaks, potholes) arrive by phone, email and social media with no single reference number, and about a third get lost between departments.
Current state
Average response time is 9.4 days, 31% of reports are closed without a field check, and there is no single map of repeat faults.
Objective
One reporting platform — a mobile app and a live map — that routes every report to the responsible maintenance team or contractor and brings response time down to 3 days by the end of 2027.
Expected scope
A citizen app, an operations console, integration with the Smart Asset Management System and existing maintenance contracts, and repeat-fault analytics by district.

Expected benefits

Time & speed

Response time down from 9.4 to 3 days

Savings

SAR 4.2M a year in maintenance savings from early detection

Customer satisfaction

Facility satisfaction up from 61% to 80%

Related lessons learned

From similar past projects (§78) — read them before evaluation

National-platform integration needs early agreements

From Unified Digital Services Platform

Integration agreements with the platform owners slipped 11 weeks because they only started after the contract award.

Recommendation: Start integration requests and SLAs during feasibility, and plan a full integration sprint.

Open the lesson

Data-migration quality sets the go-live date

From Enterprise Resource Planning (ERP) System

The second trial migration found 18% of supplier records duplicated or incomplete.

Recommendation: Estimate data cleansing as its own line in the business case, not inside contingency.

Open the lesson