Kingdom of Saudi Arabia
Board of Grievances
General Directorate of Financial Affairs — Contracts & Procurement
- Certificate no.
- 6
- Date
- 2026-03-21
- Hijri
- 2 Shawwal 1447 AH
- Reference
- PAY-2025-007-06
Interim payment certificate no. (6)
For the work of March 2026
- Contract number
- BOG/2025/007
- Etimad reference
- 2503600485
- Contract
- Mueen Digital Platform Release 4 — build & run
- Contractor
- Adalah Digital Platforms Co.
- Contractor VAT number
- 310105738640003
- Project
- Mueen Digital Platform — Release 4
- Contract period
- 2025-05-04 — 2027-03-31
- Original contract value
- 48,600,000
- Current contract value
- 51,000,000including variations of SAR 2.4M
Certificate summary (SAR)
| 1 | Total value of work completed to date | 24,030,000 |
| 2 | Less: previous certificates | (20,020,000) |
| 3 | Value of work in this certificate | 4,010,000 |
| 4 | Less: retention (10%) | (401,000) |
| 5 | Less: advance payment recovery (10%) | (401,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (802,000) |
| 8 | Net before VAT | 3,208,000 |
| 9 | Add: value added tax (15%) | 481,200 |
| 10 | Net amount payable to the contractor | 3,689,200 |
Amount in words: Three million six hundred eighty-nine thousand two hundred Saudi riyals only
Retention held up to this certificate: SAR 2.4M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Analysis & design | 7,650,000 | 4,552,000 | 734,000 | 5,286,000 | 69% |
| Licences & platform | 10,200,000 | 5,290,000 | 958,000 | 6,248,000 | 61% |
| Build & configuration | 15,300,000 | 5,945,000 | 1,264,000 | 7,209,000 | 47% |
| Systems integration | 7,650,000 | 2,336,000 | 548,000 | 2,884,000 | 38% |
| Testing & acceptance | 5,100,000 | 1,147,000 | 295,000 | 1,442,000 | 28% |
| Training & run | 5,100,000 | 750,000 | 211,000 | 961,000 | 19% |
| Total | 51,000,000 | 20,020,000 | 4,010,000 | 24,030,000 | 47% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Rayan M. Al-Shehri
Supervising engineer
Joud N. Al-Ahmadi
Project manager
Eng. Sultan F. Al-Ghamdi
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani