PRJ-2026-024On track2FeasibilityStage-Gate

Unified Judicial Operations Centre

Add to watchlist

A live command centre watching hearings, courtrooms, systems and court workloads in every region.

Budget (BAC)

SAR 110M

Actual cost

SAR 0

⁦0%⁩ of budget

Progress

⁦0%⁩

Planned ⁦0%⁩

Estimate at completion

SAR 110M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

On baseline

FeasibilityPhase ⁦2⁩ of ⁦11⁩

Next gate:Initiation4 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate17 July 2026Feasibility · Current phaseFeasibility · Current phase
  3. Gate into «Initiation»DecisionNot held yetDate4 November 2026Initiation · Not startedInitiation · Not started
  4. Gate into «Planning»DecisionNot held yetPlanning · Not startedPlanning · Not started
  5. Gate into «Approval»DecisionNot held yetApproval · Not startedApproval · Not started
  6. Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
  7. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+104⁩ days vs approved

Original baseline⁦2028-12-31⁩
Approved baseline⁦2028-12-31⁩
Current forecast⁦2029-04-14⁩
By earned schedule⁦2033-08-26⁩
Critical activities
13
of ⁦17⁩ open activities
Late activities
12
past their baseline finish
Schedule performance
0.00
earned ÷ planned value
Next milestone
in 239 days
Project plan approved
Expand allCollapse all
Activity
Unified Judicial Operations CentrePlanned: ⁦2027-01-03⁩ → ⁦2028-12-31⁩Forecast: ⁦2027-01-03⁩ → ⁦2029-04-14⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2027-01-03⁩ → ⁦2027-06-02⁩Forecast: ⁦2027-01-03⁩ → ⁦2027-06-24⁩Float: ⁦0⁩d
Project plan & baselinePlanned: ⁦2027-01-03⁩ → ⁦2027-04-05⁩Forecast: ⁦2027-01-03⁩ → ⁦2027-04-19⁩Float: ⁦0⁩d+14
Monitoring & reportingPlanned: ⁦2027-03-02⁩ → ⁦2027-06-02⁩Forecast: ⁦2027-03-10⁩ → ⁦2027-06-24⁩Float: ⁦0⁩d+22
Project plan approvedPlanned: ⁦2027-06-02⁩ → ⁦2027-06-02⁩Forecast: ⁦2027-06-24⁩ → ⁦2027-06-24⁩Float: ⁦660⁩dProject plan approved
Design & permitsPlanned: ⁦2027-04-29⁩ → ⁦2027-09-26⁩Forecast: ⁦2027-05-15⁩ → ⁦2027-11-03⁩Float: ⁦0⁩d
Detailed designPlanned: ⁦2027-04-29⁩ → ⁦2027-07-30⁩Forecast: ⁦2027-05-15⁩ → ⁦2027-08-29⁩Float: ⁦0⁩d+30
Permits & approvalsPlanned: ⁦2027-06-25⁩ → ⁦2027-09-26⁩Forecast: ⁦2027-07-20⁩ → ⁦2027-11-03⁩Float: ⁦0⁩d+38
Designs approvedPlanned: ⁦2027-09-26⁩ → ⁦2027-09-26⁩Forecast: ⁦2027-11-03⁩ → ⁦2027-11-03⁩Float: ⁦528⁩dDesigns approved
Civil worksPlanned: ⁦2027-08-22⁩ → ⁦2028-03-17⁩Forecast: ⁦2027-09-24⁩ → ⁦2028-05-19⁩Float: ⁦0⁩d
Site works & excavationPlanned: ⁦2027-08-22⁩ → ⁦2027-11-23⁩Forecast: ⁦2027-09-24⁩ → ⁦2028-01-08⁩Float: ⁦0⁩d+46
StructurePlanned: ⁦2027-10-19⁩ → ⁦2028-01-19⁩Forecast: ⁦2027-11-29⁩ → ⁦2028-03-14⁩Float: ⁦0⁩d+55
FinishesPlanned: ⁦2027-12-16⁩ → ⁦2028-03-17⁩Forecast: ⁦2028-02-03⁩ → ⁦2028-05-19⁩Float: ⁦0⁩d+63
Build completePlanned: ⁦2028-03-17⁩ → ⁦2028-03-17⁩Forecast: ⁦2028-05-19⁩ → ⁦2028-05-19⁩Float: ⁦330⁩dBuild complete
MEP worksPlanned: ⁦2028-02-11⁩ → ⁦2028-09-06⁩Forecast: ⁦2028-04-09⁩ → ⁦2028-12-03⁩Float: ⁦0⁩d
SupplyPlanned: ⁦2028-02-11⁩ → ⁦2028-05-14⁩Forecast: ⁦2028-04-09⁩ → ⁦2028-07-24⁩Float: ⁦0⁩d+71
InstallationPlanned: ⁦2028-04-09⁩ → ⁦2028-07-11⁩Forecast: ⁦2028-06-14⁩ → ⁦2028-09-28⁩Float: ⁦0⁩d+79
Testing & commissioningPlanned: ⁦2028-06-06⁩ → ⁦2028-09-06⁩Forecast: ⁦2028-08-19⁩ → ⁦2028-12-03⁩Float: ⁦0⁩d+88
Testing & acceptance completePlanned: ⁦2028-09-06⁩ → ⁦2028-09-06⁩Forecast: ⁦2028-12-03⁩ → ⁦2028-12-03⁩Float: ⁦132⁩dTesting & acceptance complete
HandoverPlanned: ⁦2028-08-03⁩ → ⁦2028-12-31⁩Forecast: ⁦2028-10-24⁩ → ⁦2029-04-14⁩Float: ⁦0⁩d
Provisional acceptancePlanned: ⁦2028-08-03⁩ → ⁦2028-11-03⁩Forecast: ⁦2028-10-24⁩ → ⁦2029-02-07⁩Float: ⁦0⁩d+96
Final acceptancePlanned: ⁦2028-09-30⁩ → ⁦2028-12-31⁩Forecast: ⁦2028-12-29⁩ → ⁦2029-04-14⁩Float: ⁦0⁩d+104
Final handoverPlanned: ⁦2028-12-31⁩ → ⁦2028-12-31⁩Forecast: ⁦2029-04-14⁩ → ⁦2029-04-14⁩Float: ⁦0⁩dFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦23⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦17⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦12⁩ activities with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.

The critical chain

In date order, to final acceptance