Unified Judicial Operations Centre
Add to watchlistA live command centre watching hearings, courtrooms, systems and court workloads in every region.
Budget (BAC)
Actual cost
0% of budget
Progress
Planned 0%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
FeasibilityPhase 2 of 11
Next gate:Initiation4 November 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate17 July 2026Feasibility · Current phaseFeasibility · Current phase
- Gate into «Initiation»DecisionNot held yetDate4 November 2026Initiation · Not startedInitiation · Not started
- Gate into «Planning»DecisionNot held yetPlanning · Not startedPlanning · Not started
- Gate into «Approval»DecisionNot held yetApproval · Not startedApproval · Not started
- Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
- Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
- Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2027-06-02 | 2027-06-24 | +22 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | At risk | 0 | Not requested |
| Designs approvedMS-G2 | Project | 2027-09-26 | 2027-11-03 | +38 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | At risk | 0 | Not requested |
| Build completeMS-G3 | Contractual | 2028-03-17 | 2028-05-19 | +63 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | At risk | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2028-09-06 | 2028-12-03 | +88 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2028-12-31 | 2029-04-14 | +104 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Deliverable flow
Display options
| Deliverable: Project plan & baseline024-D1 | Draft | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | Eng. Turki A. Al-Anazi | 2027-04-05 | V0 | 0 of 2 |
| Deliverable: Monitoring & reporting024-D2 | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.sa | Eng. Turki A. Al-Anazi | 2027-06-02 | V0 | 0 of 2 |
| Deliverable: Detailed design024-D3 | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.sa | Eng. Turki A. Al-Anazi | 2027-07-30 | V0 | 0 of 2 |
| Deliverable: Permits & approvals024-D4 | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.sa | Eng. Turki A. Al-Anazi | 2027-09-26 | V0 | 0 of 2 |
| Deliverable: Site works & excavation024-D5 | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.sa | Eng. Turki A. Al-Anazi | 2027-11-23 | V0 | 0 of 2 |
| Deliverable: Structure024-D6 | Draft | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | Eng. Turki A. Al-Anazi | 2028-01-19 | V0 | 0 of 2 |