Kingdom of Saudi Arabia
Board of Grievances
General Directorate of Financial Affairs — Contracts & Procurement
- Certificate no.
- 14
- Date
- 2025-08-31
- Hijri
- 8 Rabiʻ I 1447 AH
- Reference
- PAY-2024-006-14
Interim payment certificate no. (14)
For the work of August 2025
- Contract number
- BOG/2024/006
- Etimad reference
- 2401430082
- Contract
- Riyadh Administrative Court building — civil & MEP works
- Contractor
- Al-Ufuq General Contracting Co.
- Contractor VAT number
- 320500924170003
- Project
- Riyadh Administrative Court Building
- Contract period
- 2024-03-03 — 2026-12-31
- Original contract value
- 560,000,000
- Current contract value
- 584,000,000including variations of SAR 24M
Certificate summary (SAR)
| 1 | Total value of work completed to date | 231,950,000 |
| 2 | Less: previous certificates | (213,400,000) |
| 3 | Value of work in this certificate | 18,550,000 |
| 4 | Less: retention (10%) | (1,855,000) |
| 5 | Less: advance payment recovery (10%) | (1,855,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (3,710,000) |
| 8 | Net before VAT | 14,840,000 |
| 9 | Add: value added tax (15%) | 2,226,000 |
| 10 | Net amount payable to the contractor | 17,066,000 |
Amount in words: Seventeen million sixty-six thousand Saudi riyals only
Retention held up to this certificate: SAR 23.2M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 40,880,000 | 34,855,000 | 2,604,000 | 37,459,000 | 92% |
| Earthworks & foundations | 105,120,000 | 54,226,000 | 4,225,000 | 58,451,000 | 56% |
| Concrete & structural works | 181,040,000 | 72,726,000 | 6,369,000 | 79,095,000 | 44% |
| Mechanical, electrical & plumbing | 140,160,000 | 35,401,000 | 3,567,000 | 38,968,000 | 28% |
| Finishes & external works | 87,600,000 | 14,116,000 | 1,541,000 | 15,657,000 | 18% |
| Testing & commissioning | 29,200,000 | 2,076,000 | 244,000 | 2,320,000 | 8% |
| Total | 584,000,000 | 213,400,000 | 18,550,000 | 231,950,000 | 40% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Khalil I. Al-Dosari
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Shahad M. Al-Malki
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani