Kingdom of Saudi Arabia
Board of Grievances
General Directorate of Financial Affairs — Contracts & Procurement
- Certificate no.
- 15
- Date
- 2025-10-08
- Hijri
- 16 Rabiʻ II 1447 AH
- Reference
- PAY-2024-006-15
Interim payment certificate no. (15)
For the work of September 2025
- Contract number
- BOG/2024/006
- Etimad reference
- 2401430082
- Contract
- Riyadh Administrative Court building — civil & MEP works
- Contractor
- Al-Ufuq General Contracting Co.
- Contractor VAT number
- 320500924170003
- Project
- Riyadh Administrative Court Building
- Contract period
- 2024-03-03 — 2026-12-31
- Original contract value
- 560,000,000
- Current contract value
- 584,000,000including variations of SAR 24M
Certificate summary (SAR)
| 1 | Total value of work completed to date | 253,610,000 |
| 2 | Less: previous certificates | (231,950,000) |
| 3 | Value of work in this certificate | 21,660,000 |
| 4 | Less: retention (10%) | (2,166,000) |
| 5 | Less: advance payment recovery (10%) | (2,166,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (4,332,000) |
| 8 | Net before VAT | 17,328,000 |
| 9 | Add: value added tax (15%) | 2,599,200 |
| 10 | Net amount payable to the contractor | 19,927,200 |
Amount in words: Nineteen million nine hundred twenty-seven thousand two hundred Saudi riyals only
Retention held up to this certificate: SAR 25.4M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 40,880,000 | 37,906,000 | 2,974,000 | 40,880,000 | 100% |
| Earthworks & foundations | 105,120,000 | 59,120,000 | 4,868,000 | 63,988,000 | 61% |
| Concrete & structural works | 181,040,000 | 79,037,000 | 7,444,000 | 86,481,000 | 48% |
| Mechanical, electrical & plumbing | 140,160,000 | 38,371,000 | 4,235,000 | 42,606,000 | 30% |
| Finishes & external works | 87,600,000 | 15,275,000 | 1,844,000 | 17,119,000 | 20% |
| Testing & commissioning | 29,200,000 | 2,241,000 | 295,000 | 2,536,000 | 9% |
| Total | 584,000,000 | 231,950,000 | 21,660,000 | 253,610,000 | 43% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Khalil I. Al-Dosari
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Shahad M. Al-Malki
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani