Kingdom of Saudi Arabia
Board of Grievances
General Directorate of Financial Affairs — Contracts & Procurement
- Certificate no.
- 13
- Date
- 2025-07-23
- Hijri
- 28 Muharram 1447 AH
- Reference
- PAY-2024-006-13
Interim payment certificate no. (13)
For the work of July 2025
- Contract number
- BOG/2024/006
- Etimad reference
- 2401430082
- Contract
- Riyadh Administrative Court building — civil & MEP works
- Contractor
- Al-Ufuq General Contracting Co.
- Contractor VAT number
- 320500924170003
- Project
- Riyadh Administrative Court Building
- Contract period
- 2024-03-03 — 2026-12-31
- Original contract value
- 560,000,000
- Current contract value
- 584,000,000including variations of SAR 24M
Certificate summary (SAR)
| 1 | Total value of work completed to date | 213,400,000 |
| 2 | Less: previous certificates | (190,640,000) |
| 3 | Value of work in this certificate | 22,760,000 |
| 4 | Less: retention (10%) | (2,276,000) |
| 5 | Less: advance payment recovery (10%) | (2,276,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (4,552,000) |
| 8 | Net before VAT | 18,208,000 |
| 9 | Add: value added tax (15%) | 2,731,200 |
| 10 | Net amount payable to the contractor | 20,939,200 |
Amount in words: Twenty million nine hundred thirty-nine thousand two hundred Saudi riyals only
Retention held up to this certificate: SAR 21.3M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 40,880,000 | 31,217,000 | 3,247,000 | 34,464,000 | 84% |
| Earthworks & foundations | 105,120,000 | 48,534,000 | 5,243,000 | 53,777,000 | 51% |
| Concrete & structural works | 181,040,000 | 64,960,000 | 7,809,000 | 72,769,000 | 40% |
| Mechanical, electrical & plumbing | 140,160,000 | 31,534,000 | 4,317,000 | 35,851,000 | 26% |
| Finishes & external works | 87,600,000 | 12,553,000 | 1,852,000 | 14,405,000 | 16% |
| Testing & commissioning | 29,200,000 | 1,842,000 | 292,000 | 2,134,000 | 7% |
| Total | 584,000,000 | 190,640,000 | 22,760,000 | 213,400,000 | 37% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Khalil I. Al-Dosari
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Shahad M. Al-Malki
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani