Kingdom of Saudi Arabia
Board of Grievances
General Directorate of Financial Affairs — Contracts & Procurement
- Certificate no.
- 12
- Date
- 2025-06-15
- Hijri
- 19 Dhuʻl-Hijjah 1446 AH
- Reference
- PAY-2024-006-12
Interim payment certificate no. (12)
For the work of May 2025
- Contract number
- BOG/2024/006
- Etimad reference
- 2401430082
- Contract
- Riyadh Administrative Court building — civil & MEP works
- Contractor
- Al-Ufuq General Contracting Co.
- Contractor VAT number
- 320500924170003
- Project
- Riyadh Administrative Court Building
- Contract period
- 2024-03-03 — 2026-12-31
- Original contract value
- 560,000,000
- Current contract value
- 584,000,000including variations of SAR 24M
Certificate summary (SAR)
| 1 | Total value of work completed to date | 190,640,000 |
| 2 | Less: previous certificates | (168,810,000) |
| 3 | Value of work in this certificate | 21,830,000 |
| 4 | Less: retention (10%) | (2,183,000) |
| 5 | Less: advance payment recovery (10%) | (2,183,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (4,366,000) |
| 8 | Net before VAT | 17,464,000 |
| 9 | Add: value added tax (15%) | 2,619,600 |
| 10 | Net amount payable to the contractor | 20,083,600 |
Amount in words: Twenty million eighty-three thousand six hundred Saudi riyals only
Retention held up to this certificate: SAR 19.1M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 40,880,000 | 27,618,000 | 3,171,000 | 30,789,000 | 75% |
| Earthworks & foundations | 105,120,000 | 42,947,000 | 5,094,000 | 48,041,000 | 46% |
| Concrete & structural works | 181,040,000 | 57,524,000 | 7,484,000 | 65,008,000 | 36% |
| Mechanical, electrical & plumbing | 140,160,000 | 27,953,000 | 4,075,000 | 32,028,000 | 23% |
| Finishes & external works | 87,600,000 | 11,133,000 | 1,735,000 | 12,868,000 | 15% |
| Testing & commissioning | 29,200,000 | 1,635,000 | 271,000 | 1,906,000 | 7% |
| Total | 584,000,000 | 168,810,000 | 21,830,000 | 190,640,000 | 33% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Khalil I. Al-Dosari
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Shahad M. Al-Malki
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani