Board of GrievancesMunjaz10My actionsNotifications

Lessons learned

Lessons by category, surfaced when a similar project is created.

Published lessons
19

From ⁦17⁩ projects

Times cited
83

In later requests and projects

High impact
10

Cost days or millions

In review
2

Waiting for EPMO validation

Where lessons recur

Lessons per category · times cited

Press a category to filter the register.

Suggested for a similar project

Pick a project; lessons rank by type, phase, portfolio and proven reuse.

A Infrastructure project in Procurement

  1. 99Same project typeFits its phaseSame portfolioProven
  2. 70Same project typeFits its phase
  3. 70Same project typeFits its phase
  4. 53Same project typeProven
  5. 45Same project type

The register

Each lesson: context, what happened, impact, recommendation.

⁦21⁩ of ⁦21⁩

Loose scope in design-build contracts breeds claims

LL-2026-007 · Contracts · High impact · Published

  1. 1ContextThe Riyadh Administrative Court building is a design-build contract.
  2. 2What happenedThe contractor claimed SAR ⁦14M⁩ for requirements added after concept design: extra video-hearing courtrooms and offices for judges’ assistants.
  3. 3ImpactClaims referred to dispute resolution; the extension decision deferred.

Recommendation

Freeze the building’s functional programme with the presidents of the courts that will use it before the request goes to committee.

Captured by
Eng. Shahad M. Al-Malki
Date
2026-09-0826 Rabiʻ I 1448 AH
Applies to
Construction