Kingdom of Saudi Arabia
Board of Grievances
General Directorate of Financial Affairs — Contracts & Procurement
- Certificate no.
- 10
- Date
- 2025-03-30
- Hijri
- 1 Shawwal 1446 AH
- Reference
- PAY-2024-006-10
Interim payment certificate no. (10)
For the work of March 2025
- Contract number
- BOG/2024/006
- Etimad reference
- 2401430082
- Contract
- Riyadh Administrative Court building — civil & MEP works
- Contractor
- Al-Ufuq General Contracting Co.
- Contractor VAT number
- 320500924170003
- Project
- Riyadh Administrative Court Building
- Contract period
- 2024-03-03 — 2026-12-31
- Original contract value
- 560,000,000
- Current contract value
- 584,000,000including variations of SAR 24M
Certificate summary (SAR)
| 1 | Total value of work completed to date | 149,520,000 |
| 2 | Less: previous certificates | (126,470,000) |
| 3 | Value of work in this certificate | 23,050,000 |
| 4 | Less: retention (10%) | (2,305,000) |
| 5 | Less: advance payment recovery (10%) | (2,305,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (4,610,000) |
| 8 | Net before VAT | 18,440,000 |
| 9 | Add: value added tax (15%) | 2,766,000 |
| 10 | Net amount payable to the contractor | 21,206,000 |
Amount in words: Twenty-one million two hundred six thousand Saudi riyals only
Retention held up to this certificate: SAR 15M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 40,880,000 | 20,701,000 | 3,447,000 | 24,148,000 | 59% |
| Earthworks & foundations | 105,120,000 | 32,187,000 | 5,492,000 | 37,679,000 | 36% |
| Concrete & structural works | 181,040,000 | 43,095,000 | 7,891,000 | 50,986,000 | 28% |
| Mechanical, electrical & plumbing | 140,160,000 | 20,929,000 | 4,190,000 | 25,119,000 | 18% |
| Finishes & external works | 87,600,000 | 8,334,000 | 1,759,000 | 10,093,000 | 12% |
| Testing & commissioning | 29,200,000 | 1,224,000 | 271,000 | 1,495,000 | 5% |
| Total | 584,000,000 | 126,470,000 | 23,050,000 | 149,520,000 | 26% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Khalil I. Al-Dosari
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Shahad M. Al-Malki
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani