Board of GrievancesMunjaz10My actionsNotifications

Certificate ⁦7⁩ — November 2024

Riyadh Administrative Court building — civil & MEP works

Kingdom of Saudi Arabia

Board of Grievances

General Directorate of Financial Affairs — Contracts & Procurement

Certificate no.
7
Date
⁦2024-12-04⁩
Hijri
3 Jumada II 1446 AH
Reference
PAY-2024-006-07

Interim payment certificate no. (⁦7⁩)

For the work of November 2024

Contract number
BOG/2024/006
Etimad reference
2401430082
Contract
Riyadh Administrative Court building — civil & MEP works
Contractor
Al-Ufuq General Contracting Co.
Contractor VAT number
320500924170003
Project
Riyadh Administrative Court Building
Contract period
⁦2024-03-03⁩ — ⁦2026-12-31⁩
Original contract value
560,000,000
Current contract value
584,000,000including variations of SAR 24M

Certificate summary (SAR)

1Total value of work completed to date88,960,000
2Less: previous certificates(69,350,000)
3Value of work in this certificate19,610,000
4Less: retention (⁦10%⁩)(1,961,000)
5Less: advance payment recovery (⁦10%⁩)(1,961,000)
6Less: delay and breach penalties0
7Total deductions(3,922,000)
8Net before VAT15,688,000
9Add: value added tax (15%)2,353,200
10Net amount payable to the contractor18,041,200

Amount in words: Eighteen million forty-one thousand two hundred Saudi riyals only

Retention held up to this certificate: SAR 8.9M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation40,880,00011,328,0003,039,00014,367,000⁦35%⁩
Earthworks & foundations105,120,00017,624,0004,794,00022,418,000⁦21%⁩
Concrete & structural works181,040,00023,634,0006,701,00030,335,000⁦17%⁩
Mechanical, electrical & plumbing140,160,00011,503,0003,442,00014,945,000⁦11%⁩
Finishes & external works87,600,0004,587,0001,418,0006,005,000⁦7%⁩
Testing & commissioning29,200,000674,000216,000890,000⁦3%⁩
Total584,000,00069,350,00019,610,00088,960,000⁦15%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Khalil I. Al-Dosari

Al-Dosari⁦2024-12-04⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2024-12-06⁩

Project manager

Eng. Shahad M. Al-Malki

Al-Malki⁦2024-12-09⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2024-12-12⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2024-12-15⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2024-12-04⁩

    Eng. Khalil I. Al-Dosari

  2. Engineer verifies quantities⁦2024-12-06⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2024-12-09⁩

    Eng. Shahad M. Al-Malki · Director, Judicial Buildings & Premises

    Took 3 days

  4. Payment order prepared⁦2024-12-12⁩

    Khalid N. Al-Mutairi · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2024-12-15⁩

    Dr. Abdullah S. Al-Qahtani · President of the Board of Grievances

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Shahad M. Al-Malki → Dr. Abdullah S. Al-Qahtani

Certificate history

15 December 2024

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2024-12-15 13:00

12 December 2024

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2024-12-12 13:00

9 December 2024

  1. Approval: Eng. Shahad M. Al-Malki signed “Project manager certifies”

    2024-12-09 13:00

6 December 2024

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2024-12-06 13:00

4 December 2024

  1. Approval: Contractor signed “Certificate submitted”

    2024-12-04 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close