Kingdom of Saudi Arabia
Board of Grievances
General Directorate of Financial Affairs — Contracts & Procurement
- Certificate no.
- 6
- Date
- 2024-10-27
- Hijri
- 24 Rabiʻ II 1446 AH
- Reference
- PAY-2024-006-06
Interim payment certificate no. (6)
For the work of October 2024
- Contract number
- BOG/2024/006
- Etimad reference
- 2401430082
- Contract
- Riyadh Administrative Court building — civil & MEP works
- Contractor
- Al-Ufuq General Contracting Co.
- Contractor VAT number
- 320500924170003
- Project
- Riyadh Administrative Court Building
- Contract period
- 2024-03-03 — 2026-12-31
- Original contract value
- 560,000,000
- Current contract value
- 584,000,000including variations of SAR 24M
Certificate summary (SAR)
| 1 | Total value of work completed to date | 69,350,000 |
| 2 | Less: previous certificates | (54,380,000) |
| 3 | Value of work in this certificate | 14,970,000 |
| 4 | Less: retention (10%) | (1,497,000) |
| 5 | Less: advance payment recovery (10%) | (1,497,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (2,994,000) |
| 8 | Net before VAT | 11,976,000 |
| 9 | Add: value added tax (15%) | 1,796,400 |
| 10 | Net amount payable to the contractor | 13,772,400 |
Amount in words: Thirteen million seven hundred seventy-two thousand four hundred Saudi riyals only
Retention held up to this certificate: SAR 6.9M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 40,880,000 | 8,857,000 | 2,343,000 | 11,200,000 | 27% |
| Earthworks & foundations | 105,120,000 | 13,789,000 | 3,687,000 | 17,476,000 | 17% |
| Concrete & structural works | 181,040,000 | 18,535,000 | 5,113,000 | 23,648,000 | 13% |
| Mechanical, electrical & plumbing | 140,160,000 | 9,050,000 | 2,601,000 | 11,651,000 | 8% |
| Finishes & external works | 87,600,000 | 3,616,000 | 1,065,000 | 4,681,000 | 5% |
| Testing & commissioning | 29,200,000 | 533,000 | 161,000 | 694,000 | 2% |
| Total | 584,000,000 | 54,380,000 | 14,970,000 | 69,350,000 | 12% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Khalil I. Al-Dosari
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Shahad M. Al-Malki
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani