Kingdom of Saudi Arabia
Board of Grievances
Administrative Communications
- Number:
- ص/1448/0406
- Date:
- 8 Jumada I 1448 AH
- Corresponding to:
- 19 October 2026
- Attachments:
- 0
CONFIDENTIAL
Subject: Default notice and request for a recovery plan
United Buildings & Operations Co.
Greetings,
With reference to contract BOG/2024/003, progress has fallen to 68% against 92% planned and the supply of the new wing’s central air-conditioning units has stopped. This letter is formal notice of default under the contract.
Submit a recovery plan approved by your senior management within fourteen days, failing which the Board will act as the law allows, including withdrawing the work.
With our kind regards,
President of the Board of Grievances
Dr. Abdullah S. Al-Qahtani
Copy to:
- Ma’alem International Project Management (supervising consultant)
- Legal Department