Certificate ⁦19⁩ — February 2026

Riyadh Administrative Court building — civil & MEP works

Kingdom of Saudi Arabia

Board of Grievances

General Directorate of Financial Affairs — Contracts & Procurement

Certificate no.
19
Date
⁦2026-03-11⁩
Hijri
22 Ramadan 1447 AH
Reference
PAY-2024-006-19

Interim payment certificate no. (⁦19⁩)

For the work of February 2026

Contract number
BOG/2024/006
Etimad reference
2401430082
Contract
Riyadh Administrative Court building — civil & MEP works
Contractor
Al-Ufuq General Contracting Co.
Contractor VAT number
320500924170003
Project
Riyadh Administrative Court Building
Contract period
⁦2024-03-03⁩ — ⁦2026-12-31⁩
Original contract value
560,000,000
Current contract value
584,000,000including variations of SAR 24M

Certificate summary (SAR)

1Total value of work completed to date321,240,000
2Less: previous certificates(307,260,000)
3Value of work in this certificate13,980,000
4Less: retention (⁦10%⁩)(1,398,000)
5Less: advance payment recovery (⁦10%⁩)(1,398,000)
6Less: delay and breach penalties0
7Total deductions(2,796,000)
8Net before VAT11,184,000
9Add: value added tax (15%)1,677,600
10Net amount payable to the contractor12,861,600

Amount in words: Twelve million eight hundred sixty-one thousand six hundred Saudi riyals only

Retention held up to this certificate: SAR 32.1M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation40,880,00039,481,0001,399,00040,880,000⁦100%⁩
Earthworks & foundations105,120,00088,584,0003,369,00091,953,000⁦87%⁩
Concrete & structural works181,040,000104,731,0004,812,000109,543,000⁦61%⁩
Mechanical, electrical & plumbing140,160,00051,073,0002,895,00053,968,000⁦39%⁩
Finishes & external works87,600,00020,389,0001,295,00021,684,000⁦25%⁩
Testing & commissioning29,200,0003,002,000210,0003,212,000⁦11%⁩
Total584,000,000307,260,00013,980,000321,240,000⁦55%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Khalil I. Al-Dosari

Al-Dosari⁦2026-03-11⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-03-13⁩

Project manager

Eng. Shahad M. Al-Malki

Al-Malki⁦2026-03-16⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-03-19⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-03-22⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-03-11⁩

    Eng. Khalil I. Al-Dosari

  2. Engineer verifies quantities⁦2026-03-13⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2026-03-16⁩

    Eng. Shahad M. Al-Malki · Director, Judicial Buildings & Premises

    Took 3 days

  4. Payment order prepared⁦2026-03-19⁩

    Khalid N. Al-Mutairi · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-03-22⁩

    Dr. Abdullah S. Al-Qahtani · President of the Board of Grievances

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Shahad M. Al-Malki → Dr. Abdullah S. Al-Qahtani

Certificate history

22 March 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-03-22 13:00

19 March 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-03-19 13:00

16 March 2026

  1. Approval: Eng. Shahad M. Al-Malki signed “Project manager certifies”

    2026-03-16 13:00

13 March 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-03-13 13:00

11 March 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-03-11 09:00