10My actionsNotifications

Homes connected to the fibre network

Off track

Productivity · Fibre Optic Network Expansion

Baseline

0 homes

At go-live, ⁦2026-04-01⁩

Latest reading

17,800 homes

6 mo reading

Target after 24 months

48,000 homes

On ⁦2028-04-01⁩

Target trajectory vs realised

Monthly readings up to the last measurement, then the forecast if performance keeps its current ratio to plan.

Target trajectory vs realised
  • Realised
  • Target trajectory
  • Forecast
Target trajectory vs realised
PeriodRealisedTarget trajectory
2026-040 homes0 homes
2026-052,808.7 homes4,000 homes
2026-065,110.5 homes8,000 homes
2026-079,100 homes12,000 homes
2026-0811,593.0 homes16,000 homes
2026-0915,681.4 homes20,000 homes
2026-1017,800 homes24,000 homes
2026-11 (Forecast)19,283.3 homes26,000 homes
2026-12 (Forecast)20,766.7 homes28,000 homes
2027-01 (Forecast)22,250 homes30,000 homes
2027-02 (Forecast)23,733.3 homes32,000 homes
2027-03 (Forecast)25,216.7 homes34,000 homes
2027-04 (Forecast)26,700 homes36,000 homes
2027-05 (Forecast)27,441.7 homes37,000 homes
2027-06 (Forecast)28,183.3 homes38,000 homes
2027-07 (Forecast)28,925 homes39,000 homes
2027-08 (Forecast)29,666.7 homes40,000 homes
2027-09 (Forecast)30,408.3 homes41,000 homes
2027-10 (Forecast)31,150 homes42,000 homes
2027-11 (Forecast)31,891.7 homes43,000 homes
2027-12 (Forecast)32,633.3 homes44,000 homes
2028-01 (Forecast)33,375 homes45,000 homes
2028-02 (Forecast)34,116.7 homes46,000 homes
2028-03 (Forecast)34,858.3 homes47,000 homes
2028-04 (Forecast)35,600 homes48,000 homes

Measurement schedule

Counted from go-live on ⁦2026-04-01⁩ · data read Monthly

  1. 3

    After 3 months

    2026-07-0116 Muharram 1448 AH·Expected 12,000 homes·Actual 9,100 homes

    to plan⁦76%⁩
  2. 6

    After 6 months

    2026-10-0120 Rabiʻ II 1448 AH·Expected 24,000 homes·Actual 17,800 homes

    to plan⁦74%⁩
  3. 12

    After 12 months

    2027-04-0124 Shawwal 1448 AH·Expected 36,000 homes

    In 155 days2027-04-0124 Shawwal 1448 AH
  4. 24

    After 24 months

    2028-04-016 Dhuʻl-Qiʻdah 1449 AH·Expected 48,000 homes

    In 521 days2028-04-016 Dhuʻl-Qiʻdah 1449 AH

Evidence

5 files backing the readings

  • Measurement data extract — 6 mo

    2026-10-01 · Eng. Nayef H. Al-Buqami · ⁦138⁩ KB

  • Benefit measurement report — 6 mo

    2026-10-01 · Eng. Nayef H. Al-Buqami · ⁦986⁩ KB

  • Measurement data extract — 3 mo

    2026-07-01 · Eng. Nayef H. Al-Buqami · ⁦117⁩ KB

  • Benefit measurement report — 3 mo

    2026-07-01 · Eng. Nayef H. Al-Buqami · ⁦923⁩ KB

  • Approved benefit profile — BEN-018

    2026-02-01 · Eng. Omar H. Bawazir · ⁦412⁩ KB

Corrective actions

What is being done to bring the benefit back to plan

No actions yet — add a plan to bring the benefit back on track.

Activity

1 October 2026

  1. Milestone: Eng. Nayef H. Al-Buqami recorded the ⁦6⁩ mo reading: ⁦17,800⁩ homes

    2026-10-01 10:30

1 July 2026

  1. Milestone: Eng. Nayef H. Al-Buqami recorded the ⁦3⁩ mo reading: ⁦9,100⁩ homes

    2026-07-01 10:30

1 February 2026

  1. Approval: Eng. Omar H. Bawazir approved the benefit profile and its baseline

    2026-02-01 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close