RSK-0035Buraydah Administrative Courts Complex

Pile lengths exceeding contract quantities

12MediumOpen

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Gaps between contract and site quantities

Preventive controls

  • Re-measure quantities with the supervising consultant
  • Value engineering on the costliest items

2 / 2

Event

Pile lengths exceeding contract quantities

12MediumTrigger

Quantity variance above 5% of contract value

Contingency

Defer non-critical items to a later phase

Impact

Extra variations and contingency drawn down

SAR 8.4M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
12Medium

Residual

5
4
3
2
1
1
2
3
4
5
3Low

Exposure

SAR 8.4M

Residual

⁦75⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the EPMO director

Last reviewed 5 days ago · Outside the engine — below «high»

  1. Project manager

    Current level

    Eng. Ahmed Y. Asiri

    Currently followed up here
  2. 2

    Programme manager

    Eng. Ahmed Y. Asiri

  3. 3

    EPMO director

    Dr. Noura M. Al-Otaibi

  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the EPMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦2⁩ done
  • Re-measure quantities with the supervising consultant

    Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.sa
    In progressIn 48 days2026-12-156 Rajab 1448 AH
  • Value engineering on the costliest items

    Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.sa
    Not startedIn 48 days2026-12-156 Rajab 1448 AH

Trigger

Quantity variance above 5% of contract value

Contingency

Defer non-critical items to a later phase

Esc