RSK-0009Mueen Digital Platform — Release 4

Reuse appointment-booking components to shorten development

9OpportunityOpenOpportunity

A risk's detail, response, contingency and residual risk.

Risk statement

From enabler to opportunity to benefit — with the actions that seize it and the fallback

Enabler

The court appointment booking service is live with reusable components

Actions to seize it

  • List the reusable components with the booking-service team
  • Approve a shared architecture with the enterprise architecture office

2 / 2

Opportunity

Reuse the appointment-booking components to shorten development

9OpportunityTrigger

The component assessment shows above 60% fit

Fallback

If merging proves hard, use an adapter layer instead of a full port

Benefit

About six weeks off wave 1 development and roughly SAR 1.1M saved

SAR 1.1M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
9Opportunity

Residual

5
4
3
2
1
1
2
3
4
5
12Opportunity

Potential value

SAR 1.1M

Residual

No reduction expected — the response is to accept

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the EPMO director

Last reviewed 4 days ago · Outside the engine — below «high»

  1. Project manager

    Current level

    Eng. Sultan F. Al-Ghamdi

    Currently followed up here
  2. 2

    Programme manager

    Eng. Reem K. Al-Dosari

  3. 3

    EPMO director

    Dr. Noura M. Al-Otaibi

  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the EPMO director’s decision

Mitigation plan

Actions to seize the opportunity, with owners and dates

⁦0⁩ of ⁦2⁩ done
  • List the reusable components with the booking-service team

    Eng. Asma S. Al-HamdanEng. Asma S. Al-HamdanEnterprise ArchitectP-031a.alhamdan@bog.gov.sa
    In progressIn 8 days2026-11-0525 Jumada I 1448 AH
  • Approve a shared architecture with the enterprise architecture office

    Eng. Laila MansourEng. Laila MansourEnterprise Architecture & Integration ConsultantP-042l.mansour@bog.gov.sa
    Not startedIn 28 days2026-11-2515 Jumada II 1448 AH

Trigger

The component assessment shows above 60% fit

Fallback

If merging proves hard, use an adapter layer instead of a full port

Opportunity strategy

§26 — choose how you will seize it

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close