RSK-0007Mueen Digital Platform — Release 4

Clerks and circuit staff resisting the new digital procedures

9MediumIn progress

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Clerks and circuit staff are used to paper procedures and had little say in designing the services

Preventive controls

  • A change-ambassador network in every court
  • Hands-on training for clerks a month before launch

2 / 2

Event

Clerks and circuit staff resisting the new digital procedures

9MediumTrigger

Under 50% usage in the first month

Contingency

Retire paper registration in steps by a circular from the President

Impact

Low adoption and paper files persisting in the judicial circuits after launch

SAR 300K

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
9Medium

Residual

5
4
3
2
1
1
2
3
4
5
4Low

Exposure

SAR 300K

Residual

⁦56⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the EPMO director

Last reviewed 13 days ago · Outside the engine — below «high»

  1. Project manager

    Current level

    Eng. Sultan F. Al-Ghamdi

    Currently followed up here
  2. 2

    Programme manager

    Eng. Reem K. Al-Dosari

  3. 3

    EPMO director

    Dr. Noura M. Al-Otaibi

  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the EPMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦2⁩ done
  • A change-ambassador network in every court

    Nouf M. Al-BalawiNouf M. Al-BalawiChange Management SpecialistP-035n.albalawi@bog.gov.sa
    In progressIn 48 days2026-12-156 Rajab 1448 AH
  • Hands-on training for clerks a month before launch

    Nouf M. Al-BalawiNouf M. Al-BalawiChange Management SpecialistP-035n.albalawi@bog.gov.sa
    Not startedIn 96 days2027-02-0124 Shaʻban 1448 AH

Trigger

Under 50% usage in the first month

Contingency

Retire paper registration in steps by a circular from the President

Esc