Change Control Board — session 41
Change requests with complete files, week 43.
Held on
21 October 202613:00 – 14:10
- Held
- Minutes written
- Published
- Approved
Agenda
60 of 60 min
Approve the previous minutes
ApprovalEng. Ibrahim A. Al-Ghamdi
5 min
Riyadh court building — 150-day extension
DecisionEng. Shahad M. Al-Malki
30 min
Buraydah complex — axes 12–16 foundation redesign
DecisionEng. Ahmed Y. Asiri
25 min
Minutes
1. Approve the previous minutes
Session 40 minutes approved.
2. Riyadh court building — 150-day extension
CR-2026-006Deferred pending the independent engineer; Finance abstained.
3. Buraydah complex — axes 12–16 foundation redesign
CR-2026-010At SAR 8.4M on a revised baseline it exceeds the board’s authority; sent up to the Steering Committee.
Decisions & votes
Voting rule: Simple majority; a Finance objection on impact above SAR 5M sends it to the Steering Committee
Riyadh court building extension deferred pending the independent engineer’s report
DEC-2026-040Hold
For 4Against 0Abstain 1Carried
- Dr. Mohammed I. Al-Subaie · For
- Dr. Noura M. Al-Otaibi · For
- Khalid N. Al-Mutairi · For
- Munirah A. Al-Khalidi · Abstain
- Eng. Asma S. Al-Hamdan · Did not vote
- Eng. Ibrahim A. Al-Ghamdi · For
Action items
They show in the register and on the owner’s calendar
No actions from this meeting yet
Attendance & quorum
Quorum: Four of six members, including Finance
At least 4 voting members needed
- Dr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieDirector General, Decision Support CentreChairP-009m.alsubaie@bog.gov.saPresent
- Dr. Noura M. Al-OtaibiDr. Noura M. Al-OtaibiDirector, Projects Follow-up Office (EPMO)Vice-chairP-002n.alotaibi@bog.gov.saPresent
- Khalid N. Al-MutairiKhalid N. Al-MutairiSenior Finance & Contracts SpecialistMemberP-007k.almutairi@bog.gov.saPresent
- Munirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Financial AffairsMemberP-018m.alkhalidi@bog.gov.saPresent
- Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionSecretaryP-036i.alghamdi@bog.gov.saPresent
- Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesGuestP-022s.almalki@bog.gov.saPresent
- Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesGuestP-020a.asiri@bog.gov.saRemote
Attachments
2 files
- CR-2026-006-impact.pdfEng. Shahad M. Al-Malki · 1.2 MB
- CR-2026-010-geotech.pdfEng. Ahmed Y. Asiri · 5.3 MB