Board of GrievancesMunjaz10My actionsNotifications

Certificate ⁦12⁩ — August 2026

Backup data centre — civil & MEP works

Kingdom of Saudi Arabia

Board of Grievances

General Directorate of Financial Affairs — Contracts & Procurement

Certificate no.
12
Date
⁦2026-09-08⁩
Hijri
26 Rabiʻ I 1448 AH
Reference
PAY-2026-006

Interim payment certificate no. (⁦12⁩)

For the work of August 2026

Contract number
BOG/2025/006
Etimad reference
2503530472
Contract
Backup data centre — civil & MEP works
Contractor
Al-Ufuq General Contracting Co.
Contractor VAT number
320500924170003
Project
Board Backup Data Centre
Contract period
⁦2025-05-04⁩ — ⁦2026-11-30⁩
Original contract value
92,000,000
Current contract value
95,100,000including variations of SAR 3.1M

Certificate summary (SAR)

1Total value of work completed to date71,800,000
2Less: previous certificates(66,200,000)
3Value of work in this certificate5,600,000
4Less: retention (⁦10%⁩)(560,000)
5Less: advance payment recovery (⁦10%⁩)(560,000)
6Less: delay and breach penalties0
7Total deductions(1,120,000)
8Net before VAT4,480,000
9Add: value added tax (15%)672,000
10Net amount payable to the contractor5,152,000

Amount in words: Five million one hundred fifty-two thousand Saudi riyals only

Retention held up to this certificate: SAR 7.2M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation6,657,0006,347,000310,0006,657,000⁦100%⁩
Earthworks & foundations17,118,00016,191,000927,00017,118,000⁦100%⁩
Concrete & structural works29,481,00027,218,0002,263,00029,481,000⁦100%⁩
Mechanical, electrical & plumbing22,824,00011,592,0001,387,00012,979,000⁦57%⁩
Finishes & external works14,265,0004,238,000609,0004,847,000⁦34%⁩
Testing & commissioning4,755,000614,000104,000718,000⁦15%⁩
Total95,100,00066,200,0005,600,00071,800,000⁦75%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Khalil I. Al-Dosari

Al-Dosari⁦2026-09-08⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-09-10⁩

Project manager

Eng. Omar H. Bawazir

Bawazir⁦2026-09-13⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-09-16⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-09-19⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-09-08⁩

    Eng. Khalil I. Al-Dosari

  2. Engineer verifies quantities⁦2026-09-10⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2026-09-13⁩

    Eng. Omar H. Bawazir · Director, IT Infrastructure

    Took 3 days

  4. Payment order prepared⁦2026-09-16⁩

    Khalid N. Al-Mutairi · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-09-19⁩

    Dr. Abdullah S. Al-Qahtani · President of the Board of Grievances

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Omar H. Bawazir → Dr. Abdullah S. Al-Qahtani

Certificate history

19 September 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-09-19 13:00

16 September 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-09-16 13:00

13 September 2026

  1. Approval: Eng. Omar H. Bawazir signed “Project manager certifies”

    2026-09-13 13:00

10 September 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-09-10 13:00

8 September 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-09-08 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close