Certificate ⁦9⁩ — April 2026

Backup data centre — civil & MEP works

Kingdom of Saudi Arabia

Board of Grievances

General Directorate of Financial Affairs — Contracts & Procurement

Certificate no.
9
Date
⁦2026-05-16⁩
Hijri
29 Dhuʻl-Qiʻdah 1447 AH
Reference
PAY-2025-006-09

Interim payment certificate no. (⁦9⁩)

For the work of April 2026

Contract number
BOG/2025/006
Etimad reference
2503530472
Contract
Backup data centre — civil & MEP works
Contractor
Al-Ufuq General Contracting Co.
Contractor VAT number
320500924170003
Project
Board Backup Data Centre
Contract period
⁦2025-05-04⁩ — ⁦2026-11-30⁩
Original contract value
92,000,000
Current contract value
95,100,000including variations of SAR 3.1M

Certificate summary (SAR)

1Total value of work completed to date58,300,000
2Less: previous certificates(52,450,000)
3Value of work in this certificate5,850,000
4Less: retention (⁦10%⁩)(585,000)
5Less: advance payment recovery (⁦10%⁩)(585,000)
6Less: delay and breach penalties0
7Total deductions(1,170,000)
8Net before VAT4,680,000
9Add: value added tax (15%)702,000
10Net amount payable to the contractor5,382,000

Amount in words: Five million three hundred eighty-two thousand Saudi riyals only

Retention held up to this certificate: SAR 5.8M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation6,657,0006,161,000496,0006,657,000⁦100%⁩
Earthworks & foundations17,118,00015,729,0001,389,00017,118,000⁦100%⁩
Concrete & structural works29,481,00018,166,0002,047,00020,213,000⁦69%⁩
Mechanical, electrical & plumbing22,824,0008,540,0001,254,0009,794,000⁦43%⁩
Finishes & external works14,265,0003,365,000570,0003,935,000⁦28%⁩
Testing & commissioning4,755,000489,00094,000583,000⁦12%⁩
Total95,100,00052,450,0005,850,00058,300,000⁦61%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Khalil I. Al-Dosari

Al-Dosari⁦2026-05-16⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-05-18⁩

Project manager

Eng. Omar H. Bawazir

Bawazir⁦2026-05-21⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-05-24⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-05-27⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-05-16⁩

    Eng. Khalil I. Al-Dosari

  2. Engineer verifies quantities⁦2026-05-18⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2026-05-21⁩

    Eng. Omar H. Bawazir · Director, IT Infrastructure

    Took 3 days

  4. Payment order prepared⁦2026-05-24⁩

    Khalid N. Al-Mutairi · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-05-27⁩

    Dr. Abdullah S. Al-Qahtani · President of the Board of Grievances

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Omar H. Bawazir → Dr. Abdullah S. Al-Qahtani

Certificate history

27 May 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-05-27 13:00

24 May 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-05-24 13:00

21 May 2026

  1. Approval: Eng. Omar H. Bawazir signed “Project manager certifies”

    2026-05-21 13:00

18 May 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-05-18 13:00

16 May 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-05-16 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close