10My actionsNotifications

RSK-0023East Waha Wastewater Treatment Plant

Failures in the main force mains during commissioning

12MediumOpen

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Higher technical complexity than estimated and several systems to integrate

Preventive controls

  • An independent technical design review
  • Early tests on a pilot scope

2 / 2

Event

Failures in the main force mains during commissioning

12MediumTrigger

Any major acceptance test fails

Contingency

A temporary workaround until the fix is complete

Impact

Rework and later testing and commissioning

SAR 5.6M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
12Medium

Residual

5
4
3
2
1
1
2
3
4
5
3Low

Exposure

SAR 5.6M

Residual

⁦75⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 9 days ago · Outside the engine — below «high»

  1. Project manager

    Current level

    Eng. Waleed O. Al-Juhani

    Currently followed up here
  2. 2

    Programme manager

    Eng. Mishari K. Al-Otaibi

  3. 3

    PMO director

    Dr. Noura M. Al-Otaibi

  4. 4

    Executive committee

    Eng. Abdullah S. Al-Qahtani

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦2⁩ done
  • An independent technical design review

    Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa
    In progressIn 53 days2026-12-2011 Rajab 1448 AH
  • Early tests on a pilot scope

    Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Utilities & Public ServicesP-021w.aljuhani@alwaha.gov.sa
    Not startedIn 53 days2026-12-2011 Rajab 1448 AH

Trigger

Any major acceptance test fails

Contingency

A temporary workaround until the fix is complete

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close