RSK-0016Board of Grievances Headquarters, Riyadh
Late handover of the northern plot and utility diversions in zones 3 and 4
A risk's detail, response, contingency and residual risk.
Risk statement
From cause to event to impact — with the preventive controls before the event and the contingency after it
Cause
Late handover of the northern part of the site, and utility diversions in zones 3 and 4
Preventive controls
- A joint committee with the Saudi Electricity Company to schedule the diversions
- Re-sequence works to start with zones 1 and 2
1 / 2
Event
Late handover of the northern plot and utility diversions in zones 3 and 4
No part of the land handed over before the end of November
Contingency
Move laydown areas and site offices to zone 2 until the land is fully handed over
Impact
The Supreme Administrative Court building and its linked buildings at least 75 days late, and extension claims from the contractor
Assessment
The level before and after the response
Inherent
Residual
Exposure
SAR 31M
Residual
40% off the score
Score trend
Last six months
- Score
- Target residual
Escalation path
Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the EPMO director
Last reviewed 4 days ago
Project manager
Eng. Ahmed Y. Asiri
Currently followed up hereProgramme manager
Current levelEng. Ahmed Y. Asiri
Automatically at 15 days unreviewed · in 11 days- 3
EPMO director
Dr. Noura M. Al-Otaibi
Automatically at 20 days unreviewed · in 16 days - 4
Executive committee
Dr. Abdullah S. Al-Qahtani
By the EPMO director’s decision
Mitigation plan
Each action with its owner and date — tick it off when complete
A joint committee with the Saudi Electricity Company to schedule the diversions
Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.saIn progressIn 8 days2026-11-0525 Jumada I 1448 AHRe-sequence works to start with zones 1 and 2
Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.saDone2026-10-152026-10-154 Jumada I 1448 AH
Trigger
No part of the land handed over before the end of November
Contingency
Move laydown areas and site offices to zone 2 until the land is fully handed over