RSK-0016Board of Grievances Headquarters, Riyadh

Late handover of the northern plot and utility diversions in zones 3 and 4

20CriticalEscalated

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Late handover of the northern part of the site, and utility diversions in zones 3 and 4

Preventive controls

  • A joint committee with the Saudi Electricity Company to schedule the diversions
  • Re-sequence works to start with zones 1 and 2

1 / 2

Event

Late handover of the northern plot and utility diversions in zones 3 and 4

20CriticalTrigger

No part of the land handed over before the end of November

Contingency

Move laydown areas and site offices to zone 2 until the land is fully handed over

Impact

The Supreme Administrative Court building and its linked buildings at least 75 days late, and extension claims from the contractor

SAR 31M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
20Critical

Residual

5
4
3
2
1
1
2
3
4
5
12Medium

Exposure

SAR 31M

Residual

⁦40⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the EPMO director

Last reviewed 4 days ago

  1. Project manager

    Eng. Ahmed Y. Asiri

    Currently followed up here
  2. Programme manager

    Current level

    Eng. Ahmed Y. Asiri

    Automatically at 15 days unreviewed · in 11 days
  3. 3

    EPMO director

    Dr. Noura M. Al-Otaibi

    Automatically at 20 days unreviewed · in 16 days
  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the EPMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦1⁩ of ⁦2⁩ done
  • A joint committee with the Saudi Electricity Company to schedule the diversions

    Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.sa
    In progressIn 8 days2026-11-0525 Jumada I 1448 AH
  • Re-sequence works to start with zones 1 and 2

    Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.sa
    Done⁦2026-10-15⁩2026-10-154 Jumada I 1448 AH

Trigger

No part of the land handed over before the end of November

Contingency

Move laydown areas and site offices to zone 2 until the land is fully handed over