Board of GrievancesMunjaz10My actionsNotifications

RSK-0015Board of Grievances Headquarters, Riyadh

Steel and concrete price rises driving price-adjustment claims

20CriticalEscalated

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Steel up 22% and ready-mix concrete up 15% since award

Preventive controls

  • Apply the price-adjustment formula under the Government Tenders and Procurement Law
  • Negotiate advance purchase of the remaining steel

2 / 2

Event

Steel and concrete price rises driving price-adjustment claims

20CriticalTrigger

Approved claims above SAR 30M

Contingency

A top-up request to the Ministry of Finance in the 2027 budget

Impact

Price-adjustment claims near SAR 48M, above the project contingency

SAR 48M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
20Critical

Residual

5
4
3
2
1
1
2
3
4
5
12Medium

Exposure

SAR 48M

Residual

⁦40⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the EPMO director

Last reviewed 4 days ago

  1. Project manager

    Eng. Ahmed Y. Asiri

    Currently followed up here
  2. Programme manager

    Current level

    Eng. Ahmed Y. Asiri

    Automatically at 15 days unreviewed · in 11 days
  3. 3

    EPMO director

    Dr. Noura M. Al-Otaibi

    Automatically at 20 days unreviewed · in 16 days
  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the EPMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦2⁩ done
  • Apply the price-adjustment formula under the Government Tenders and Procurement Law

    Khalid N. Al-MutairiKhalid N. Al-MutairiSenior Finance & Contracts SpecialistP-007k.almutairi@bog.gov.sa
    In progressIn 13 days2026-11-1030 Jumada I 1448 AH
  • Negotiate advance purchase of the remaining steel

    Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.sa
    In progressIn 18 days2026-11-155 Jumada II 1448 AH

Trigger

Approved claims above SAR 30M

Contingency

A top-up request to the Ministry of Finance in the 2027 budget

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close