10My actionsNotifications

Strategic objectives achievement report

Strategic reportInternal

Al-Waha Region Development Authority · Q3 2026

MunjazPMO PLATFORM

Strategic report

Strategic objectives achievement report

Al-Waha Region Development Authority

Period
Q3 2026
Generated
7 October 202626 Rabiʻ II 1448 AH
Submitted to
The Board and the Executive Committee
Owner
Dr. Amal F. Al-Sudairi

Prepared by the Enterprise PMO — automatically, on Munjaz

Munjaz · RPT-08 · page ⁦1⁩ of ⁦5⁩Internal
Strategic objectives achievement reportAl-Waha Region Development Authority

Executive summary

Written by Copilot from system data — review before sending

0 of 12 strategic objectives have met their annual target so far; average achievement is 77% against a 85% target.

The scope holds 36 projects with a budget of SAR 5.15B: 18 on track and 6 red or critical. Weighted progress is 43% against 52% planned, spend SAR 2.41B, and EAC SAR 5.56B (SAR 407.7M over).

12 projects are more than a month behind baseline; the worst: Government Offices Complex (152 days), East Waha Wastewater Treatment Plant (126 days), Waterfront Rehabilitation (95 days).

Key figures

Projects
36
Budget
SAR 5.2B
Spent
SAR 2.4B
EAC
SAR 5.6B
Progress
⁦44%⁩ / ⁦54%⁩
SPI
0.85
CPI
0.93
High risks
18

Project health mix

  • On track 18
  • At risk 10
  • Off track 4
  • Critical 2
  • On hold 2
Munjaz · RPT-08 · page ⁦2⁩ of ⁦5⁩Internal
Strategic objectives achievement reportAl-Waha Region Development Authority

Strategic objectives

ObjectiveAchievedTarget
SO-1.1Build integrated infrastructure connecting the region’s cities and governorates⁦74%⁩⁦85%⁩
SO-1.2Raise energy and water efficiency and cut emissions⁦69%⁩⁦80%⁩
SO-1.3Improve quality of life and the urban landscape⁦77%⁩⁦80%⁩
SO-2.1Attract quality investment to the region⁦76%⁩⁦85%⁩
SO-2.2Enable public–private partnership⁦70%⁩⁦80%⁩
SO-2.3Ease doing business and speed up licensing⁦79%⁩⁦85%⁩
SO-3.1Deliver unified, beneficiary-centred digital services⁦72%⁩⁦85%⁩
SO-3.2Build secure, reliable, cloud-first technology⁦88%⁩⁦90%⁩
SO-3.3Make the most of data and AI⁦66%⁩⁦80%⁩
SO-4.1Embed project governance and performance management⁦85%⁩⁦90%⁩
SO-4.2Spend efficiently and grow own revenues⁦83%⁩⁦90%⁩
SO-4.3Develop human capital and organisational culture⁦82%⁩⁦85%⁩
Munjaz · RPT-08 · page ⁦3⁩ of ⁦5⁩Internal
Strategic objectives achievement reportAl-Waha Region Development Authority

Projects with the most at stake

ProjectBudgetProgressSlipHealth
Northern Ring Road Development — Phase 2SAR 1.2B⁦42%⁩74 daysOff track
Government Offices ComplexSAR 640M⁦57%⁩152 daysCritical
Abha – Al-Baha Road DualisationSAR 520M⁦2%⁩—On track
East Waha Wastewater Treatment PlantSAR 412M⁦68%⁩126 daysCritical
Wadi Al-Rummah BridgeSAR 345M⁦44%⁩64 daysOff track
Waterfront RehabilitationSAR 286M⁦39%⁩95 daysOff track
Northern Logistics Zone InfrastructureSAR 238M⁦33%⁩28 daysAt risk
Regional Emergency & Safety CentreSAR 210M⁦2%⁩184 daysOn hold
Al-Waha Central ParkSAR 158M⁦52%⁩12 daysAt risk
National Backup Data CentreSAR 148M⁦72%⁩38 daysAt risk
Fibre Optic Network ExpansionSAR 132M⁦55%⁩33 daysAt risk
Smart City Integrated Operations CentreSAR 110M⁦0%⁩—On track
Munjaz · RPT-08 · page ⁦4⁩ of ⁦5⁩Internal
Strategic objectives achievement reportAl-Waha Region Development Authority

Highest-exposure risks

RiskScoreExposure
Main contractor cash-flow distress and unpaid subcontractorsEast Waha Wastewater Treatment Plant25SAR 36M
Steel and asphalt price rises driving price-adjustment claimsNorthern Ring Road Development — Phase 220SAR 48M
Contractor financial claims piling up over unapproved variationsGovernment Offices Complex20SAR 41M
Late land acquisition and utility diversions in sections 3 and 4Northern Ring Road Development — Phase 220SAR 31M
Unforeseen ground conditions at the pier foundations in the wadi bedWadi Al-Rummah Bridge20SAR 27M
Late land handover and title deed from the owning entityRegional Emergency & Safety Centre20SAR 12M
Marine protection costs up after the hydrographic surveyWaterfront Rehabilitation16SAR 22.5M

Decisions needed

  1. 1

    Pay subcontractors directly at the wastewater treatment plant

    The PMO recommends paying directly out of certificate 22 and deducting it from the main contractor’s dues.

  2. 2

    Refer the Government Offices Complex claims to arbitration

    Legal recommends referral, with an independent engineer assessing the extension request in parallel.

  3. 3

    Approve the updated recovery plan for the Unified Digital Services Platform

    The Steering Committee recommends conditional approval with a monthly progress review.

  4. 4

    Release SAR 22M of infrastructure reserve to speed up land acquisition

    Infrastructure recommends two tranches tied to site handovers.

Munjaz · RPT-08 · page ⁦5⁩ of ⁦5⁩Internal
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close