Digital portfolio report for the Steering Committee

Portfolio reportConfidential

Digital Transformation Portfolio · October 2026 — ahead of 3 November

MunjazPMO PLATFORM

Portfolio report

Digital portfolio report for the Steering Committee

Digital Transformation Portfolio

Period
October 2026 — ahead of 3 November
Generated
13 October 20262 Jumada I 1448 AH
Submitted to
The Board and the Executive Committee
Owner
Faisal A. Al-Shehri

Prepared by the Enterprise PMO — automatically, on Munjaz

Munjaz · RPT-03 · page ⁦1⁩ of ⁦5⁩Confidential
Digital portfolio report for the Steering CommitteeAl-Waha Region Development Authority

Executive summary

Written by Copilot from system data — review before sending

The Digital Transformation portfolio holds 7 projects with an approved SAR 190M; SAR 124.6M is committed and SAR 98.6M spent. EAC is SAR 183.9M — within budget by SAR 6.1M. Five projects are green, two amber, none red.

The main concern is the Unified Digital Services Platform (SAR 86.4M, 45% of the portfolio): 42 days behind baseline with a 74% chance of further slippage within 45 days. Its strategic effect shows in beneficiary satisfaction stuck at 74% against an 85% target. The rest is on track: the Investor Portal is 91% done and the mobile app runs at SPI 1.02.

Three decisions are asked of the committee: (1) move commercial-licence renewal to wave 2 rather than adding it now (+21 days, SAR 1.85M); (2) approve the internal resource reallocation to integration; (3) send the vendor a formal letter on replacing its integration engineers.

Key figures

Projects
7
Budget
SAR 180.3M
Spent
SAR 98.6M
EAC
SAR 183.9M
Progress
⁦55%⁩ / ⁦60%⁩
SPI
0.92
CPI
0.98
High risks
2

Project health mix

  • On track 5
  • At risk 2
Munjaz · RPT-03 · page ⁦2⁩ of ⁦5⁩Confidential
Digital portfolio report for the Steering CommitteeAl-Waha Region Development Authority

Budget and EAC by portfolio

Budget and EAC by portfolio
  • Budget
  • EAC
Budget and EAC by portfolio
CategoryBudgetEAC
Investor PortalSAR 18.4MSAR 18M
Unified Digital Services PlatformSAR 86.4MSAR 90M
Services Mobile AppSAR 12.6MSAR 12.1M
Data Governance & Master Data ManagementSAR 21.5MSAR 22.6M
Analytics & AI PlatformSAR 28MSAR 28M
Unified e-Appointments PlatformSAR 8.2MSAR 8M
Government Innovation LabSAR 5.2MSAR 5.2M
Munjaz · RPT-03 · page ⁦3⁩ of ⁦5⁩Confidential
Digital portfolio report for the Steering CommitteeAl-Waha Region Development Authority

Projects with the most at stake

ProjectBudgetProgressSlipHealth
Unified Digital Services PlatformSAR 86.4M⁦58%⁩42 daysAt risk
Analytics & AI PlatformSAR 28M⁦1%⁩—On track
Data Governance & Master Data ManagementSAR 21.5M⁦62%⁩18 daysAt risk
Investor PortalSAR 18.4M⁦91%⁩—On track
Services Mobile AppSAR 12.6M⁦64%⁩—On track
Unified e-Appointments PlatformSAR 8.2M⁦100%⁩20 daysOn track
Government Innovation LabSAR 5.2M⁦0%⁩—On track
Munjaz · RPT-03 · page ⁦4⁩ of ⁦5⁩Confidential
Digital portfolio report for the Steering CommitteeAl-Waha Region Development Authority

Highest-exposure risks

RiskScoreExposure
Nafath and SADAD integration interfaces not ready on timeUnified Digital Services Platform16SAR 2.4M
Shortage of integration and back-end engineers on the vendor teamUnified Digital Services Platform16SAR 1.9M
Late sign-off of licensing-service requirements by the owning departmentsUnified Digital Services Platform12SAR 1.2M
Possible critical findings in the pre-launch penetration testUnified Digital Services Platform12SAR 600K
Incomplete migration of beneficiary data from legacy systemsUnified Digital Services Platform9SAR 750K
Too few accredited data owners in the departmentsData Governance & Master Data Management9SAR 650K
Mobile-app team competing with the platform for the same peopleUnified Digital Services Platform9SAR 520K

Decisions needed

  1. 1

    Approve the updated recovery plan for the Unified Digital Services Platform

    The Steering Committee recommends conditional approval with a monthly progress review.

  2. 2

    Approve the October Steering Committee minutes

    Reviewed by the committee secretary; no open comments.

Munjaz · RPT-03 · page ⁦5⁩ of ⁦5⁩Confidential