10My actionsNotifications

Monthly executive portfolio report

Monthly reportConfidential

Al-Waha Region Development Authority · September 2026

MunjazPMO PLATFORM

Monthly report

Monthly executive portfolio report

Al-Waha Region Development Authority

Period
September 2026
Generated
5 October 202624 Rabiʻ II 1448 AH
Submitted to
The Board and the Executive Committee
Owner
Dr. Noura M. Al-Otaibi

Prepared by the Enterprise PMO — automatically, on Munjaz

Munjaz · RPT-01 · page ⁦1⁩ of ⁦5⁩Confidential
Monthly executive portfolio reportAl-Waha Region Development Authority

Executive summary

Written by Copilot from system data — review before sending

The scope holds 36 projects with a budget of SAR 5.15B: 18 on track and 6 red or critical. Weighted progress is 43% against 52% planned, spend SAR 2.41B, and EAC SAR 5.56B (SAR 407.7M over).

12 projects are more than a month behind baseline; the worst: Government Offices Complex (152 days), East Waha Wastewater Treatment Plant (126 days), Waterfront Rehabilitation (95 days).

18 high risks are open with SAR 403.4M of exposure; the decisions needed centre on contractor distress and the large change requests.

Key figures

Projects
36
Budget
SAR 5.2B
Spent
SAR 2.4B
EAC
SAR 5.6B
Progress
⁦44%⁩ / ⁦54%⁩
SPI
0.85
CPI
0.93
High risks
18

Project health mix

  • On track 18
  • At risk 10
  • Off track 4
  • Critical 2
  • On hold 2
Munjaz · RPT-01 · page ⁦2⁩ of ⁦5⁩Confidential
Monthly executive portfolio reportAl-Waha Region Development Authority

Budget and EAC by portfolio

Budget and EAC by portfolio
  • Budget
  • EAC
Budget and EAC by portfolio
CategoryBudgetEAC
Digital Transformation PortfolioSAR 180.3MSAR 183.9M
Capital Projects PortfolioSAR 1.3BSAR 1.5B
Technology Projects PortfolioSAR 352.7MSAR 376M
Sustainability PortfolioSAR 650MSAR 726M
Infrastructure PortfolioSAR 2.6BSAR 2.8B
Institutional Development PortfolioSAR 30.5MSAR 30.5M

Monthly spend 2026

Monthly spend 2026
  • Actual
  • Planned
  • Forecast
Monthly spend 2026
PeriodActualPlanned
JanSAR 79MSAR 86M
FebSAR 84MSAR 92M
MarSAR 101MSAR 118M
AprSAR 109MSAR 124M
MaySAR 117MSAR 131M
JunSAR 113MSAR 128M
JulSAR 96MSAR 112M
AugSAR 104MSAR 121M
SepSAR 115MSAR 137M
OctSAR 121MSAR 142M
Nov (Forecast)SAR 132MSAR 148M
Dec (Forecast)SAR 158MSAR 171M
Munjaz · RPT-01 · page ⁦3⁩ of ⁦5⁩Confidential
Monthly executive portfolio reportAl-Waha Region Development Authority

Projects with the most at stake

ProjectBudgetProgressSlipHealth
Northern Ring Road Development — Phase 2SAR 1.2B⁦42%⁩74 daysOff track
Government Offices ComplexSAR 640M⁦57%⁩152 daysCritical
Abha – Al-Baha Road DualisationSAR 520M⁦2%⁩—On track
East Waha Wastewater Treatment PlantSAR 412M⁦68%⁩126 daysCritical
Wadi Al-Rummah BridgeSAR 345M⁦44%⁩64 daysOff track
Waterfront RehabilitationSAR 286M⁦39%⁩95 daysOff track
Northern Logistics Zone InfrastructureSAR 238M⁦33%⁩28 daysAt risk
Regional Emergency & Safety CentreSAR 210M⁦2%⁩184 daysOn hold
Al-Waha Central ParkSAR 158M⁦52%⁩12 daysAt risk
National Backup Data CentreSAR 148M⁦72%⁩38 daysAt risk
Fibre Optic Network ExpansionSAR 132M⁦55%⁩33 daysAt risk
Smart City Integrated Operations CentreSAR 110M⁦0%⁩—On track
Munjaz · RPT-01 · page ⁦4⁩ of ⁦5⁩Confidential
Monthly executive portfolio reportAl-Waha Region Development Authority

Highest-exposure risks

RiskScoreExposure
Main contractor cash-flow distress and unpaid subcontractorsEast Waha Wastewater Treatment Plant25SAR 36M
Steel and asphalt price rises driving price-adjustment claimsNorthern Ring Road Development — Phase 220SAR 48M
Contractor financial claims piling up over unapproved variationsGovernment Offices Complex20SAR 41M
Late land acquisition and utility diversions in sections 3 and 4Northern Ring Road Development — Phase 220SAR 31M
Unforeseen ground conditions at the pier foundations in the wadi bedWadi Al-Rummah Bridge20SAR 27M
Late land handover and title deed from the owning entityRegional Emergency & Safety Centre20SAR 12M
Marine protection costs up after the hydrographic surveyWaterfront Rehabilitation16SAR 22.5M

Decisions needed

  1. 1

    Pay subcontractors directly at the wastewater treatment plant

    The PMO recommends paying directly out of certificate 22 and deducting it from the main contractor’s dues.

  2. 2

    Refer the Government Offices Complex claims to arbitration

    Legal recommends referral, with an independent engineer assessing the extension request in parallel.

  3. 3

    Approve the updated recovery plan for the Unified Digital Services Platform

    The Steering Committee recommends conditional approval with a monthly progress review.

  4. 4

    Release SAR 22M of infrastructure reserve to speed up land acquisition

    Infrastructure recommends two tranches tied to site handovers.

Munjaz · RPT-01 · page ⁦5⁩ of ⁦5⁩Confidential
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close