Contractor recovery meeting — Dammam courts complex
On-site recovery of the Dammam courts complex contractor.
Held on
27 October 202612:00 – 13:40
- Held
- Minutes written
- Published
- Approved
Project meeting — no quorum required
Agenda
70 of 90 min
Overdue subcontractor payments
DiscussionKhalid N. Al-Mutairi
40 min
Underground tanks water-tightness test
DiscussionEng. Waleed O. Al-Juhani
30 min
Minutes
Saved as you type
1. Overdue subcontractor payments
CTR-2024-0032. Underground tanks water-tightness test
ISS-0114
Decisions & votes
No decisions recorded
Record the decision and put it to a vote if needed.
Action items
They show in the register and on the owner’s calendar
- Pay subcontractors directly from the next certificateOpenIn 8 days2026-11-0525 Jumada I 1448 AH
ACT-0308Munirah A. Al-Khalidi
Attendance & quorum
Project meeting — no quorum required
- Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesGuestP-010t.alanazi@bog.gov.saPresent
- Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesGuestP-013b.alshammari@bog.gov.saPresent
- Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceGuestP-021w.aljuhani@bog.gov.saPresent
- Khalid N. Al-MutairiKhalid N. Al-MutairiSenior Finance & Contracts SpecialistGuestP-007k.almutairi@bog.gov.saPresent
- Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyGuestP-028m.alotaibi@bog.gov.saRemote
Attachments
1 file
- Site-inspection-Oct-27.pdfEng. Waleed O. Al-Juhani · 18.0 MB