EPMO Committee — gate reviews
October gate reviews.
Held on
14 October 202611:00 – 12:35
- Held
- Minutes written
- Published
- Approved
Agenda
80 of 90 min
Approve the previous minutes
ApprovalDr. Noura M. Al-Otaibi
5 min
Board ERP planning gate
DecisionDana S. Al-Saleh
45 min
Earlier gate conditions — follow-up
For informationTariq S. Al-Yami
30 min
Minutes
Approved and locked
1. Approve the previous minutes
Approved.
2. Board ERP planning gate
PRJ-2026-001Sent back: the schedule ignores the Etimad integration delay.
3. Earlier gate conditions — follow-up
7 of 9 conditions met.
Decisions & votes
Voting rule: Simple majority; the chair holds the casting vote
Board ERP project plan sent back for rework
DEC-2026-038Rework
For 5Against 1Abstain 1Carried
- Dr. Noura M. Al-Otaibi · For
- Dr. Amal F. Al-Sudairi · For
- Faisal A. Al-Shehri · For
- Tariq S. Al-Yami · For
- Eng. Ahmed Y. Asiri · Abstain
- Dana S. Al-Saleh · Against
- Haifa S. Al-Ruwaili · For
Dana Al-Saleh, as the project’s owner, objected and asked for two weeks.
Action items
They show in the register and on the owner’s calendar
No actions from this meeting yet
Attendance & quorum
Quorum: Four of eight members, including the chair or vice-chair
At least 4 voting members needed
- Dr. Noura M. Al-OtaibiDr. Noura M. Al-OtaibiDirector, Projects Follow-up Office (EPMO)ChairP-002n.alotaibi@bog.gov.saPresent
- Faisal A. Al-ShehriFaisal A. Al-ShehriDirector, Digital Judicial Services Centre & Digital Justice Portfolio ManagerMemberP-003f.alshehri@bog.gov.saPresent
- Dr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategic Planning & PerformanceVice-chairP-015a.alsudairi@bog.gov.saPresent
- Tariq S. Al-YamiTariq S. Al-YamiHead, Development & Performance Measurement OfficeMemberP-040t.alyami@bog.gov.saPresent
- Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsMemberP-025d.alsaleh@bog.gov.saPresent
- Haifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystMemberP-037h.alruwaili@bog.gov.saRemote
Attachments
1 file
- ERP-gate-pack.pdfDana S. Al-Saleh · 1.9 MB