Board of GrievancesMunjaz10My actionsNotifications

Lessons learned

Lessons by category, surfaced when a similar project is created.

Published lessons
19

From ⁦17⁩ projects

Times cited
83

In later requests and projects

High impact
10

Cost days or millions

In review
2

Waiting for EPMO validation

Where lessons recur

Lessons per category · times cited

Press a category to filter the register.

Suggested for a similar project

Pick a project; lessons rank by type, phase, portfolio and proven reuse.

A Infrastructure project in Procurement

  1. 99Same project typeFits its phaseSame portfolioProven
  2. 70Same project typeFits its phase
  3. 70Same project typeFits its phase
  4. 53Same project typeProven
  5. 45Same project type

The register

Each lesson: context, what happened, impact, recommendation.

⁦21⁩ of ⁦21⁩

Grid-connection approvals take 4–6 months

LL-2026-010 · Stakeholders · Medium impact · Published

  1. 1ContextSolar power for court buildings.
  2. 2What happenedThe Saudi Electricity Company took five months to approve connecting the first ⁦12⁩ court buildings.
  3. 3ImpactThe first energisation milestone moved a full quarter.

Recommendation

Put the grid operator’s approval on the critical path of any renewable-energy request.

Captured by
Eng. Mishari K. Al-Otaibi
Date
2026-04-1527 Shawwal 1447 AH
Applies to
Infrastructure · Construction

Where it was used (⁦4⁩)