BOG 2030 execution plan — draft

ConfidentialIn reviewV1Checked out to Abeer H. Al-Shamrani

Draft execution plan for the BOG ⁦2030⁩ strategy: the four pillars, objectives, initiatives and KPIs.

More

Confidential

Kingdom of Saudi Arabia

Board of Grievances

Projects Follow-up Office (EPMO)

Code
DOC-0219
Version
V1
Date
2026-10-18

BOG ⁦2030⁩ execution plan — draft

Execution Plan for the BOG 2030 Strategy

⁦1⁩. Executive summary

This report gives the position of Execution Plan for the BOG ⁦2030⁩ Strategy to date: ⁦70%⁩ complete against ⁦68%⁩ planned, SPI ⁦1.03⁩, CPI ⁦1.00⁩, and an estimate at completion of SAR ⁦3.2M⁩.

Project
Execution Plan for the BOG ⁦2030⁩ Strategy (⁦PRJ-2026-028⁩)
Project manager
Abeer H. Al-Shamrani
Budget
SAR ⁦3.2M⁩
Progress
⁦70%⁩ actual against ⁦68%⁩ planned
Forecast finish
⁦2026-12-15⁩

⁦2⁩. Key findings

  • All planned milestones of the period met except one deferred
  • Actual spend rose in line with the work done
  • Three high risks under treatment, each with a named owner

⁦3⁩. Recommendations & decisions needed

  • Approve the proposed treatment of the high risks
  • Track the open findings with the vendor weekly

Prepared by

Abeer H. Al-Shamrani
Issued from Munjaz — valid only once approved electronically1 / 1