Board of GrievancesMunjaz10My actionsNotifications

Geotechnical report — axes 12–16

InternalReturnedV2

Geotechnical report for axes ⁦12⁩ to ⁦16⁩ on the Buraydah administrative courts complex site, with foundation recommendations.

More
Showing version:

Internal

Kingdom of Saudi Arabia

Board of Grievances

Projects Follow-up Office (EPMO)

Code
DOC-0215
Version
V2
Date
2026-10-18

Geotechnical report — axes ⁦12–16⁩

Buraydah Administrative Courts Complex

⁦1⁩. Executive summary

This report gives the position of Buraydah Administrative Courts Complex to date: ⁦44%⁩ complete against ⁦55%⁩ planned, SPI ⁦0.80⁩, CPI ⁦0.95⁩, and an estimate at completion of SAR ⁦363.2M⁩.

Project
Buraydah Administrative Courts Complex (⁦PRJ-2026-020⁩)
Project manager
Eng. Ahmed Y. Asiri
Budget
SAR ⁦345.0M⁩
Progress
⁦44%⁩ actual against ⁦55%⁩ planned
Forecast finish
⁦2027-08-03⁩

⁦2⁩. Key findings

  • All planned milestones of the period met except one deferred
  • Actual spend rose in line with the work done
  • Three high risks under treatment, each with a named owner

⁦3⁩. Recommendations & decisions needed

  • Approve the proposed treatment of the high risks
  • Track the open findings with the vendor weekly

Prepared by

Eng. Ahmed Y. Asiri
Issued from Munjaz — valid only once approved electronically1 / 1

Internal

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close