10My actionsNotifications

Capacity & resource allocation report

Resource reportInternal

Al-Waha Region Development Authority · October 2026

MunjazPMO PLATFORM

Resource report

Capacity & resource allocation report

Al-Waha Region Development Authority

Period
October 2026
Generated
19 October 20268 Jumada I 1448 AH
Submitted to
The Board and the Executive Committee
Owner
Dr. Noura M. Al-Otaibi

Prepared by the Enterprise PMO — automatically, on Munjaz

Munjaz · RPT-07 · page ⁦1⁩ of ⁦5⁩Internal
Capacity & resource allocation reportAl-Waha Region Development Authority

Executive summary

Written by Copilot from system data — review before sending

14 staff and consultants are allocated beyond capacity (up to 135%), mostly in integration, analysis and testing — the skills now constraining the digital projects.

The scope holds 36 projects with a budget of SAR 5.15B: 18 on track and 6 red or critical. Weighted progress is 43% against 52% planned, spend SAR 2.41B, and EAC SAR 5.56B (SAR 407.7M over).

12 projects are more than a month behind baseline; the worst: Government Offices Complex (152 days), East Waha Wastewater Treatment Plant (126 days), Waterfront Rehabilitation (95 days).

Key figures

Projects
36
Budget
SAR 5.2B
Spent
SAR 2.4B
EAC
SAR 5.6B
Progress
⁦44%⁩ / ⁦54%⁩
SPI
0.85
CPI
0.93
High risks
18

Project health mix

  • On track 18
  • At risk 10
  • Off track 4
  • Critical 2
  • On hold 2
Munjaz · RPT-07 · page ⁦2⁩ of ⁦5⁩Internal
Capacity & resource allocation reportAl-Waha Region Development Authority

Allocated beyond capacity

  • Hussam T. Al-QurashiSenior Software Engineer – Integration⁦135%⁩
  • Eng. Waleed O. Al-JuhaniDirector, Utilities & Public Services⁦130%⁩
  • Eng. Ahmed Y. AsiriDirector General, Roads & Bridges⁦125%⁩
  • Lama S. Al-HarbiSenior Business Analyst⁦120%⁩
  • Dana S. Al-SalehDirector, Enterprise Applications⁦120%⁩
  • Eng. Sultan F. Al-GhamdiProject Manager, Unified Digital Services Platform⁦115%⁩
  • Eng. Omar H. BawazirDirector, IT Infrastructure⁦115%⁩
  • Eng. Turki A. Al-AnaziVP, Projects & Infrastructure⁦110%⁩
  • Eng. Abdulrahman S. Al-HarbiDeputy, Capital Projects⁦110%⁩
  • Eng. Shahad M. Al-MalkiDirector, Government Buildings & Facilities⁦110%⁩
  • Joud N. Al-AhmadiQA & Testing Specialist⁦110%⁩
  • Dr. Noura M. Al-OtaibiDirector, Enterprise PMO⁦105%⁩
  • Eng. Bandar M. Al-ShammariDeputy, Infrastructure⁦105%⁩
  • Eng. Mishari K. Al-OtaibiDirector, Sustainability & Environment⁦105%⁩
Munjaz · RPT-07 · page ⁦3⁩ of ⁦5⁩Internal
Capacity & resource allocation reportAl-Waha Region Development Authority

Projects with the most at stake

ProjectBudgetProgressSlipHealth
Northern Ring Road Development — Phase 2SAR 1.2B⁦42%⁩74 daysOff track
Government Offices ComplexSAR 640M⁦57%⁩152 daysCritical
Abha – Al-Baha Road DualisationSAR 520M⁦2%⁩—On track
East Waha Wastewater Treatment PlantSAR 412M⁦68%⁩126 daysCritical
Wadi Al-Rummah BridgeSAR 345M⁦44%⁩64 daysOff track
Waterfront RehabilitationSAR 286M⁦39%⁩95 daysOff track
Northern Logistics Zone InfrastructureSAR 238M⁦33%⁩28 daysAt risk
Regional Emergency & Safety CentreSAR 210M⁦2%⁩184 daysOn hold
Al-Waha Central ParkSAR 158M⁦52%⁩12 daysAt risk
National Backup Data CentreSAR 148M⁦72%⁩38 daysAt risk
Fibre Optic Network ExpansionSAR 132M⁦55%⁩33 daysAt risk
Smart City Integrated Operations CentreSAR 110M⁦0%⁩—On track
Munjaz · RPT-07 · page ⁦4⁩ of ⁦5⁩Internal
Capacity & resource allocation reportAl-Waha Region Development Authority

Highest-exposure risks

RiskScoreExposure
Main contractor cash-flow distress and unpaid subcontractorsEast Waha Wastewater Treatment Plant25SAR 36M
Steel and asphalt price rises driving price-adjustment claimsNorthern Ring Road Development — Phase 220SAR 48M
Contractor financial claims piling up over unapproved variationsGovernment Offices Complex20SAR 41M
Late land acquisition and utility diversions in sections 3 and 4Northern Ring Road Development — Phase 220SAR 31M
Unforeseen ground conditions at the pier foundations in the wadi bedWadi Al-Rummah Bridge20SAR 27M
Late land handover and title deed from the owning entityRegional Emergency & Safety Centre20SAR 12M
Marine protection costs up after the hydrographic surveyWaterfront Rehabilitation16SAR 22.5M

Decisions needed

  1. 1

    Pay subcontractors directly at the wastewater treatment plant

    The PMO recommends paying directly out of certificate 22 and deducting it from the main contractor’s dues.

  2. 2

    Refer the Government Offices Complex claims to arbitration

    Legal recommends referral, with an independent engineer assessing the extension request in parallel.

  3. 3

    Approve the updated recovery plan for the Unified Digital Services Platform

    The Steering Committee recommends conditional approval with a monthly progress review.

  4. 4

    Release SAR 22M of infrastructure reserve to speed up land acquisition

    Infrastructure recommends two tranches tied to site handovers.

Munjaz · RPT-07 · page ⁦5⁩ of ⁦5⁩Internal
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close