Weekly project status report
Al-Waha Region Development Authority · Week 43 — 18–22 October 2026
Weekly report
Weekly project status report
Al-Waha Region Development Authority
- Period
- Week 43 — 18–22 October 2026
- Generated
- 25 October 202614 Jumada I 1448 AH
- Submitted to
- The Board and the Executive Committee
- Owner
- Dr. Noura M. Al-Otaibi
Prepared by the Enterprise PMO — automatically, on Munjaz
Executive summary
Written by Copilot from system data — review before sending
The scope holds 36 projects with a budget of SAR 5.15B: 18 on track and 6 red or critical. Weighted progress is 43% against 52% planned, spend SAR 2.41B, and EAC SAR 5.56B (SAR 407.7M over).
12 projects are more than a month behind baseline; the worst: Government Offices Complex (152 days), East Waha Wastewater Treatment Plant (126 days), Waterfront Rehabilitation (95 days).
18 high risks are open with SAR 403.4M of exposure; the decisions needed centre on contractor distress and the large change requests.
Key figures
- Projects
- 36
- Budget
- SAR 5.2B
- Spent
- SAR 2.4B
- EAC
- SAR 5.6B
- Progress
- 44% / 54%
- SPI
- 0.85
- CPI
- 0.93
- High risks
- 18
Project health mix
- On track 18
- At risk 10
- Off track 4
- Critical 2
- On hold 2
Budget and EAC by portfolio
- Budget
- EAC
| Category | Budget | EAC |
|---|---|---|
| Digital Transformation Portfolio | SAR 180.3M | SAR 183.9M |
| Capital Projects Portfolio | SAR 1.3B | SAR 1.5B |
| Technology Projects Portfolio | SAR 352.7M | SAR 376M |
| Sustainability Portfolio | SAR 650M | SAR 726M |
| Infrastructure Portfolio | SAR 2.6B | SAR 2.8B |
| Institutional Development Portfolio | SAR 30.5M | SAR 30.5M |
Monthly spend 2026
- Actual
- Planned
- Forecast
| Period | Actual | Planned |
|---|---|---|
| Jan | SAR 79M | SAR 86M |
| Feb | SAR 84M | SAR 92M |
| Mar | SAR 101M | SAR 118M |
| Apr | SAR 109M | SAR 124M |
| May | SAR 117M | SAR 131M |
| Jun | SAR 113M | SAR 128M |
| Jul | SAR 96M | SAR 112M |
| Aug | SAR 104M | SAR 121M |
| Sep | SAR 115M | SAR 137M |
| Oct | SAR 121M | SAR 142M |
| Nov (Forecast) | SAR 132M | SAR 148M |
| Dec (Forecast) | SAR 158M | SAR 171M |
Projects with the most at stake
| Project | Budget | Progress | Slip | Health |
|---|---|---|---|---|
| Northern Ring Road Development — Phase 2 | SAR 1.2B | 42% | 74 days | Off track |
| Government Offices Complex | SAR 640M | 57% | 152 days | Critical |
| Abha – Al-Baha Road Dualisation | SAR 520M | 2% | — | On track |
| East Waha Wastewater Treatment Plant | SAR 412M | 68% | 126 days | Critical |
| Wadi Al-Rummah Bridge | SAR 345M | 44% | 64 days | Off track |
| Waterfront Rehabilitation | SAR 286M | 39% | 95 days | Off track |
| Northern Logistics Zone Infrastructure | SAR 238M | 33% | 28 days | At risk |
| Regional Emergency & Safety Centre | SAR 210M | 2% | 184 days | On hold |
| Al-Waha Central Park | SAR 158M | 52% | 12 days | At risk |
| National Backup Data Centre | SAR 148M | 72% | 38 days | At risk |
| Fibre Optic Network Expansion | SAR 132M | 55% | 33 days | At risk |
| Smart City Integrated Operations Centre | SAR 110M | 0% | — | On track |
Highest-exposure risks
| Risk | Score | Exposure |
|---|---|---|
| Main contractor cash-flow distress and unpaid subcontractorsEast Waha Wastewater Treatment Plant | 25 | SAR 36M |
| Steel and asphalt price rises driving price-adjustment claimsNorthern Ring Road Development — Phase 2 | 20 | SAR 48M |
| Contractor financial claims piling up over unapproved variationsGovernment Offices Complex | 20 | SAR 41M |
| Late land acquisition and utility diversions in sections 3 and 4Northern Ring Road Development — Phase 2 | 20 | SAR 31M |
| Unforeseen ground conditions at the pier foundations in the wadi bedWadi Al-Rummah Bridge | 20 | SAR 27M |
| Late land handover and title deed from the owning entityRegional Emergency & Safety Centre | 20 | SAR 12M |
| Marine protection costs up after the hydrographic surveyWaterfront Rehabilitation | 16 | SAR 22.5M |
Decisions needed
- 1
Pay subcontractors directly at the wastewater treatment plant
The PMO recommends paying directly out of certificate 22 and deducting it from the main contractor’s dues.
- 2
Refer the Government Offices Complex claims to arbitration
Legal recommends referral, with an independent engineer assessing the extension request in parallel.
- 3
Approve the updated recovery plan for the Unified Digital Services Platform
The Steering Committee recommends conditional approval with a monthly progress review.
- 4
Release SAR 22M of infrastructure reserve to speed up land acquisition
Infrastructure recommends two tranches tied to site handovers.